|
Crossgates
Area Replacement
This is subsystem is one of the Authority's oldest systems, dating to
the early 1960's. The area in question, running from Palipetz Drive up
the valley to Gateshead drive was identified as having multiple defects,
thereby allowing extraneous water to enter the sanitary sewer system.
Several options to repair the sanitary sewer were evaluated, due to its
close proximity to several of the homes along Scarlborough Lane, it was
decide best to replace the line and locate it several feet from the existing
line. The existing line will left in place to carry ground water away
from the new sanitary sewer ditch. This concept is what is known as "parallel
sewer". The project is currently in the final design phase, with
anticipation that advertisements to solicit competitive bids to complete
work being let in Early 2005. As this is a rather large project, and will
affect several residential properties, a public meeting will be held to
inform the residents of the work and to answer any questions that they
may have. Those affected residents will receive notice once the plans
are finalized. The project is estimated to carry a price tag in the neighborhood
of $319,000.00
Return to Home Page
Brush
Run Vactor Receiving Station
The Authority recently took delivery of 2004 Vactor combination hydraulic
sewer cleaner and vacuum truck to replace its antiquated hydraulic sewer
cleaner. The new unit not only has the capabilities to use high-pressure
water for cleaning of the sanitary sewers, but also permits for the vacuuming
of the debris removed. As this material usually consists of a lot of water,
a facility is required that will permit the material to be de-watered
prior to transport to the sanitary landfill for ultimate disposal. The
vactor receiving station consists of a large concrete tank with an under-drain
system that permits the liquid to be pumped back to the treatment plant
for treatment, the tank has access for a skid steer loader to access the
in order to load the debris for disposal. The current plans call for conversion
of an unused tank located at the Brush Run WPCP. The project is designed;
however, completion has been placed on hold. The Authority may need to
use this space for an additional treatment process that may become necessary
as a result of the US EPA placing a TMDL (Total Maximum Daily Load) allowances
for phosphorus on the stream to which the plant discharges.
The Authority has received confirmation from
the US EPA that a TMDL will not be imposed on the stream, and therefore
the Authority plans to proceed with construction during 2005.
Return to Home Page
Friar
Lane Area Lining Project
This area has been identified as contributing large amounts of inflow/infiltration
into the sanitary sewer system, and has been targeted for some type of
rehabilitation. Current plans call for the lining of the old VCP sanitary
sewers with new plastic pipe. This method requires little or no excavation,
as the new pipe is pulled through the existing pipe from the manholes.
The only excavation required is the area where the house lateral will
need to be reconnected to the new pipe. This method was chosen as it provides
for less disruption of the neighborhood. The area currently under consideration
is both sides of Friar Lane up to and including Merlin Drive, as well
as a small portion of Camelford Road. Plans are currently being developed,
and barring any unforeseen circumstances; the project is scheduled to
be completed during 2004. Those residents affected by the project will
receive written notification once the plans are finalized.
Return to Home Page
Stonehenge
Area Grouting and Point Repairs
Approximately 10,000 linear feet of sanitary sewer pipe in this area has
been targeted for rehabilitation in early 2005. The method of rehabilitation
consists of pressure testing each joint of the sanitary sewer pipe and
those joints that do not pass the test will have a chemical grout injected
into them. All manholes in the area of the project will also tested and
sealed using chemical grout. In addition, any defects in the pipe will
be repaired by the placement of cured in place pipe repairs. This method
requires no excavation to complete, as a resin impregnated liner is pulled
to the defect from the existing manholes and then inflated to adhere to
the host pipe and allowed to cure, thereby becoming one with host pipe.
All the property owners in the affected area will receive written notification
prior to the start of the project.
Return to Home Page
D.C.
WPCP De-Chlorination Facilities
The PTSA has made application to the PA DEP for a permit to install De-chlorination
facilities at is Donaldson Crossroads WPCP. The installation will permit
the introduction of Sodium Bisulfite into the wastewater as it leaves
the chlorine contact tank, this will serve to remove the vast majority
of the residual chlorine before the final effluent enters Chartiers Creek.
The project will consist of installation of a chemical storage and feed
room with related equipment, a new outfall pipe with a vault for chemical
addition, as well as some minor equipment enhancements. The project is
being completed in order to comply with the more stringent discharge limits
for residual chlorine placed upon the Authority in its new NPDES permit
issued by the PA DEP and US EPA.
Return to Home Page
Collection
System Rehabilitation Efforts
The Authority has recently awarded two separate contract totaling nearly
$100,000 to complete rehabilitation efforts tot he sanitary sewers in
the Fieldbrook and McNary Plans of the Township. On contract is for the
testing of each joint within the pipe and then chemically grouting any
joint that fails that test. The second contract consists of the placement
of several CIPP (Cured in Place Pipe) liners to correct some minor defects
in the sewer pipe. Neither of these contracts will require any excavation
to perform, and upon completion, approximately 10,000 LF of sewer will
have been completely rehabilitated including the manholes within the sub
system. Final administrative issues are being addressed at this time,
and upon completion of those items, a Notice to Proceed will be issued
to the selected contractors.
Return to Home Page
Valley
Brook Interceptor Capacity Augmentation
The Authority is in the process of securing approval from the PA Department
of Environmental Protection for its plans to augment the capacity in a
portion of its Valley Brook Interceptor Sewer. The augmentation will be
accomplished by replacing old vetrified clay pipe with larger diameter
PVC pipe. Approximately 2300 LF of pipe will be replaced beginning in
the vicinity of Brusters Ice Creme and going west toward the treatment
plant. The Authority hopes to have secured approval and to let the project
out for the competitive bidding process by February 2002 with construction
to commence in the Spring of 2002.
Return to Home Page
BR WPCP
Bar Screen Washing Press
The Authority Board of Directors at its February meeting awarded a contract
for the purchase and installation of a bar screen washing press at its
Brush Run WPCP. The washer will not only remove any organic material left
in the screenings, but will also compact the amount of screenings collected,
thereby reducing the cost of disposal. The total project cost, including
engineering and design, is estimated at $80,000.00 and is scheduled to
be completed by the end of summer.
Return to Home Page
Pipe
Bursting Projects
This form of pipe replacement is fast becoming popular in the sewer industry,
as there is very little or no excavation required. The process is actually
quite simple; a pneumatic pipe bursting tool is inserted into the pipe
which "bursts" the old pipe while expanders push it out of the
way. The new pipe is attached to the tool and is being pulled into place
as the old pipe is burst.
The Authority has recently completed two pipe-bursting projects:
- Nancy Court Area: Replacement of approximately 126 LF of deteriorated
8" clay pipe with 8" High Density Polyethylene pipe (HPDE).
This method was chosen as the line crosses beneath Waterfall Way.
- Waterdam Road Area: This segment of line was replaced, as there was
a need to increase the hydraulic capacity. The line being about 35'
deep and crossing beneath the State owned roadway, pipe bursting was
selected. This consisted of replacement of nearly 280 LF of 10"
concrete pipe with 16" HDPE pipe.
Return to Home Page
Complete
Sub-system Rehabilitation Projects
The East Highland Drive Area was targeted for rehabilitation as it was
identified as contributing excess inflow and infiltration into the sewer
system. Two different methods of rehabilitation were chosen to accomplish
the task. The first being the traditional method of excavation. This portion
involved the excavation and replacement of approximately 3300 LF of 8"
VCP with 8 PVC pipe and the replacement of several manholes, as well as
the installation of "inspection ports" on all service laterals.
The other chosen method was that of yet another trenchless technology
method, using the formed in place lining procedure. This method uses a
pipe that is basically deformed to allow it to be pulled through the existing
pipe from manhole to manhole. Once in the existing pipe, the new pipe
is reformed to its original shape using a combination of steam and pressure.
Approximately 2510 LF of pipe was rehabilitated with this technology.
All of the service laterals along theses segments also had an inspection
port installed. Total cost for both projects was in the neighborhood of
$500,000.00.
Return to Home Page
Grouting
Projects
The Authority routinely undertakes projects to have the joints in its
sanitary sewer system tested and any joint failing to hold the required
test pressure is then grouted using a chemical grout. Several of the recently
completed areas include:
- Stonebrook Drive Area: 10,666 LF of 8" sanitary sewer
- Marella Manor Area: 6,250 LF of 8" sanitary sewer
- Valleybrook Interceptor: 4726 LF consisting of 12", 15",
and 18" sanitary sewer
In conjunction with the testing and grouting
in Marella Manor, the Authority also performed several CIPP (Cured in
Place Pipe) repairs. This method is also one of the trenchless methods.
It consists of pulling a fiberglass resin impregnated sock into the sewer
line to the area requiring repair. The sock is then expanded and allowed
to cure in place thereby adhering itself to the host pipe.
Return to Home Page
Capacity
Augmentation Projects
Occasionally the need arises to augment the amount of capacity in the
intercepting sewers due to growth and/or excessive I/I, which cannot be
removed cost effectively. Just this past fall, the Authority installed
approximately 600 LF of Relief Sewer along the lower portion of Oakwood
Road in the vicinity of its DC WPCP. This line will become active during
periods of high flow conditions conveying additional flow to the treatment
plant, thereby eliminating any potential overflow that may have otherwise
occurred in this area.
Return to Home Page
|